Projects

Our Client

Supply, Installation and Commissioning of High Pressure Air Compressor. (200 barg)

DESCRIPTION

01 Compressor, 200 barg and 15 m3/min capacity
Lifting and Installation
Inter Skid Piping
Inter Skid Instrumentation and Electrical

Electrical Works

Cable Laying, Earthing Work
Panel Transmission, Loop Testing and Verification

Commissioning

Pre-Commissioning Checks and Verification
Commissioning, Start up and Performance Testing.

Mechanical Works

Design, Fabrication and Testing of 4500 Litres Ultra High Pressure Air Storage Vessels (250 Barg)

Structure Fabrication and Welding

Skid Structure

Interconnected Piping between Compressors and Point of Use

Equipment Erection

Compressor
Pressure Vessels with related accessories (Safety Valves, Pressure Gauges, Pressure Regulators)


Our Client

DESIGN, FABRICATION AND INSTALLATION OF CARBONATORS (CHEMICAL PROCESS SILOS)

Mechanical Works

Cutting of Top End Dish
Cutting of Existing Shell having dia of 5 meters
Fabrication and Welding of New Shell
Installation and Welding of New Dish End
Removal and Reinstallation of Heating Coils
Internal Surface Coating.
Radiographic Testing

Commissioning

Pre-Commissioning Checks and Verification
Commissioning and Performance Testing.


Our Client

DESIGN, FABRICATION AND CONSTRUCTION OF CONE SILO

DESCRIPTION

Design, Fabrication and Construction of 25 Tons Cone Silos.

Earth Works

Sand Cutting and Filling, Leveling, Grading and Compaction
Gravel Laying (Hard Capping)

Civil Works

Heavy Concrete Uplift Foundation


Our Client

DESIGN, FABRICATION AND INSTALLATION OF HIGH PRESSURE DOUBLE BOTTOM TANKS

Mechanical Works

Fabrication and Welding
Radiographic Testing
Ultrasonic Testing

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


Our Client

SUPPLY AND INSTALLATION OF 4 Nos. CARBON FILTER BAGS SEALED COMPARTMENTS

Mechanical Works

Fabrication of 280 Nos. Filter Bags Hanging Roof and Bottoms
Refurbishment of 10 Nos. Mechanical Doors
Design and Fabrication of New Walkways, including ladders

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


Our Client

REMOVAL AND LAYING OF 4 KMS. SEA WATER PIPELINE OF 500 MM DIA

Earth Works

Desiting of Intake Sea Water Channel
Commissioning
Pre Commissioning Checks and Verification
Commissioning and Performance Testing

Civil Works

Excavation and Trenching
Construction of Culverts
Preparation of Bricks Support
Lowering, Back Filling and Crowning


Our Client

LAYING OF 5 KMS. FRESH WATER LINE OF 200 MM DIA

Mechanical Work

Welding
Commissioning
Pre Commissioning Checks and Verification
Commissioning and Performance Testing

Civil Works

Excavation and Trenching
Preparation of Bricks Support
Lowering, Back Filling and Crowning


Our Client

REPAIRING OF MAIN KILN OF SODA ASH INCLUDING INSTALLATION OF REFRACTORY

Mechanical Work

Fabrication and Welding
Argon Arc Welding
Radiographic Testing
Ultrasonic Testing
Base Rollers Alignment

Civil Works

Fixing of Refractory Bricks


Our Client

DESIGN AND CONSTRUCTION OF 50,000 GALLONS CLARIFIER TANK INCLUDING SPILLWAY

Mechanical Work

Design, Fabrication and Installation of Walkway Bridge
Installation of Grinder Blade
Installation of Gear Box
Installation of Suction pump in the tank

Electrical Work

Cable Laying
Earthing Work

Civil Works

RCC Foundation
RCC Columns
RCC Cone Ball

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


Our Client

DESIGN, FABRICATION and INSTALLATION OF STAINLESS STEEL CAUSTIC SODA RECOVERY PLANT STORAGE TANK OF 20,000 LTRS

Mechanical Work

Design, Fabrication and Installation of Walkway Bridge
Installation of Grinder Blade
Installation of Gear Box
Installation of Suction pump in the tank

Electrical Work

Cable Laying
Earthing Work

Civil Works

RCC Foundation
RCC Columns
RCC Cone Ball

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


Our Client

WAUKESHA 1 MW DIESEL GENERATOR OVERHAUL AT OMV KADANWARI

Mechanical Work

Dismantling of Engine
Crank Replacement
Reassembly of Engine

Electrical Work

Refurbishment of Alternator
Servicing and Refurbishment of Alternator including bearing replacement

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


Our Client

SUPPLY AND LAYING OF 1000 RFT POLYETHYLINE PIPES

Mechanical Work

Overhauling of Suction Pump

Earth Works

Horizontal Boring for laying of Pipe under the Main road

Civil Works

Excavation
Construction of Pits


Our Client

REFURBISHMENT OF LARGE DIA SEA WATER INTAKE VALVES FOR K ELECTRIC
(2000 MM, 1800 MM, 1500 MM, 1000 MM, 500 MM)

Mechanical Work

Dismantling of Valve
Repair and Refurbishment of the Valve
Welding
Machining
Polishing
Rubberizing
Hydro Testing


Our Client

REFURBISHMENT OF HIGH PRESSURE STAINLESS STEEL VALVES FOR UEP

Mechanical Work

Dismantling of Valve
Chroming
Replacement of Seals
Hydro Testing


Our Client

SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF PARKER ASPHALT PLANT

Description

Supply, Installation, Testing and
Commissioning of 3 Nos. Parker Asphalt
Plants

Commissioning

Pre Commissioning Checks and Verification
Commissioning and Performance Testing


SUPPLY AND INSTALLATION OF OVERHEAD CRANES, HOISTS AND STEEL STRUCTURES

Description

Customers – Yunus Textile Mills, International Textile Mills, K Electric, Times Ceramincs, Healthtek Pharma, Inteng Gear Automotive Ltd, Master Papers Ltd

Electrical Work

Cable Laying
Earthing Work

Mechanical Work

Design, Fabrication and Installation of Side Girders
Design, Fabrication and Installation of Rails on Side Girders
Design, Fabrication and Installation of Travelling Beams
Design, Fabrication and Installation of Gentries


MAINTENANCE OF COMPRESSORS

Description

Routine as well as Major Maintenance have been carried out on hundreds of Air Compressors as well as Process Compressors. Our teams have extensive hands on experience to work on Centrifugal, Rotary Screw, Reciprocating, Air as well as Gas Compressors. Process Blowers

Electrical Work

Motor Winding
Rotor Balancing
Bearing Replacement
Megger Testing
Dry Run Testing

Instrumentation Work

Calibration of Sensors, Pressure Transducers, Temperature Sensors
Testing of Solenoid Valve Coils
PLC Repair and Reprogramming

Mechanical Work

Dismantling and Installation of Bearing, Seals, Rotor Assembly and Diffusers on Centrifugal Compressors
Dismantling and Installation of Airend Rebuilt Kit on Rotary Screw Compressors
Dismantling and Installation of Pistons, Piston Rings, Crank Shaft Assembly, Crosshead Bushings
Refurbishment of Internal Slides and Piston
Setting of Slide Clearance
Replacement of Seals
Refurbishment of Inlet and Outlet Valves
Refurbishment of Valve Seats
Replacement of Stuffing Box
Cold Metal Spray
Machining and Polishing
Balancing of Rotors


Our Clients

SUPPLY AND LAYING OF SCHEDULE PIPES

Description

Laying of Different Sized Schedule Pipes for Compressed Air, Fire Line and Cooling Water for a diversified range of customers like K Electric BQPS 1 and BQPS 2, PAF Base Faisal, Oil and Gas Development Company Ltd, Civil Works Organization, Abbott Laboratories, Glaxo Smith Kline, Health Tek Industries, Pakistan Railways, Army Welfare Trust, PIA White Body Hangar, Zeal Pak Cement, Attock Cement, Lucky Cement and Hundreds of Textile Mills all over the country.

Civil Works

Digging of Trench for Underground Piping

Mechanical Work

Piping, Fabrication and Welding.
Structure Fabrication and Welding

Commissioning

Pre-Commissioning Checks and Verification
Commissioning, Start up and Performance Testing.


has been added to your cart:
Checkout